An electric aerial platform is only productive when it is charged. That sounds obvious, and yet the most common reason a new electric platform loses its first weeks on site is that nobody planned where it would charge, when, or from what supply.
This guide covers the infrastructure decisions that have to be made before the machine arrives, and the workflow that keeps it working.
Quick answer
Plan for three things: a dedicated charging circuit sized for the charger rather than a shared site socket, a charging position that is within reach of the work area and clear of lifting operations, and a charging window that fits the site's shift pattern. Where shifts are long, opportunity charging during breaks and material handling is more effective than one overnight charge, because the cost of a full cycle is often longer than the gap between shifts.
Sizing the electrical supply
Charger power draw is the first number to establish, and it is not the same as battery capacity. A charger that fills a large battery overnight may draw far less power than one that fills a smaller battery in two hours.
| Parameter | What to establish | Consequence if ignored |
|---|---|---|
| Battery capacity (kWh) | Usable capacity, not nominal | Endurance estimates are wrong |
| Charger output (kW) | Output power, not input | Charge time estimates are wrong |
| Charger input current (A) | At the site voltage | Circuit breaker and cable sizing wrong |
| Charge time to 80% | The practical working figure | Shift planning fails at the end of the day |
| Charge time to 100% | Needed for balance charging | Battery life shortened if never fully charged |
| Simultaneous machines | Number charging at once | Site supply overloaded at shift end |
If a site has several electric machines, the peak load occurs when they all return at the end of the shift and all start charging. Staggered charging or a load management system avoids the peak and usually removes the need to upgrade the supply.
Charging position: three constraints
- Distance to the work face. The machine should be able to reach a charger without crossing the whole site. A travelling time of more than ten minutes each way turns a short top-up into a lost half hour.
- Clear of lifting operations. The charging position must be outside the working radius of cranes and outside exclusion zones. Charging leads are a trip and snag hazard.
- Weather and security. Outdoor charging needs a weatherproof connection point and cable management. Overnight charging needs the area to be secure or the machine to be immobilised.
| Option | Advantage | Limitation |
|---|---|---|
| Fixed charge point at site entrance | Simple, one install, secure | Long travel to the work face |
| Charge point at the work zone edge | Short travel, good for opportunity charging | Requires power distribution across the site |
| Mobile charging unit on a trailer | Follows the work, no fixed install | Needs a power source wherever it stops |
| Battery swap | Continuous operation possible | Requires spare batteries and a handling method |
| Overhead cable with a reel | Keeps leads off the ground | Reduces flexibility of position |
Opportunity charging versus full-cycle charging
Lead-acid and lithium systems behave differently here, and the difference changes the workflow.
| Chemistry | Opportunity charging | Full cycle requirement | Workflow implication |
|---|---|---|---|
| Flooded lead-acid | Acceptable but limited | Regular full charge required to prevent sulphation | Charge at shift end, every day |
| AGM / gel lead-acid | Better tolerance | Periodic full charge still required | Opportunity charge during breaks, full charge overnight |
| Lithium iron phosphate (LiFePO4) | Well suited | Balance charge recommended periodically | Opportunity charging is the default strategy |
| Lithium NMC | Well suited, high power acceptance | Balance charge periodic | Fast top-ups during breaks are efficient |
Where the machine uses lithium, a fifteen-minute top-up at each break can be worth more than an extra hour of overnight charging, because the last portion of a charge cycle is slow while the middle is fast.
Matching the workflow to the machine
| Shift pattern | Charging routine | Watch point |
|---|---|---|
| Single 8-hour shift | One overnight full charge | Confirm overnight charge completes before shift start |
| Two 8-hour shifts, same machine | Opportunity charge at changeover plus overnight | Charge time may be shorter than the changeover gap |
| Two 12-hour shifts, same machine | Opportunity charging plus a battery swap or a second machine | A single battery rarely covers 24 hours |
| Seasonal peak work | Full charge every night plus a spare battery | Peak weeks exceed normal duty |
| Intermittent use | Charge after each use, not weekly | Deep discharge damages lead-acid; lithium self-discharges slowly but should not be stored empty |
Cables, connectors and site safety
- Specify the connector type and confirm it matches the site standard; mixing connector families across a fleet creates adapter clutter and failure points.
- Provide cable management so leads do not lie across walkways. Cable ramps or overhead reels are both acceptable; loose leads are not.
- Protect charging equipment from vehicle impact with bollards or a physical barrier.
- Provide an emergency stop or isolator at each charge point.
- Keep the charging area clear of combustible material, particularly where lead-acid batteries vent hydrogen during charging.
- Confirm the charger is rated for the ambient temperature range of the site; chargers derate in high heat.
Measuring whether the plan is working
Four measurements tell you whether the charging plan is matched to the workflow. All four are cheap to collect.
| Metric | Target | What a shortfall indicates |
|---|---|---|
| State of charge at shift start | Above 95% | Charge window too short or charger undersized |
| State of charge at shift end | Above 20% | Endurance margin adequate; below 20% means the duty exceeds the battery |
| Charging interruptions per week | Zero | Connector or supply problem, or the position is being obstructed |
| Travel time to charge point | Under 10 minutes each way | Position poorly chosen; consider a second point |
Common planning failures
| Failure | Symptom | Correction |
|---|---|---|
| Shared site socket used for charging | Breaker trips when other equipment runs | Dedicated circuit sized for the charger |
| Charging point at the far end of the site | Machine returns late and undercharged | Relocate or add a second point |
| No cable management | Damaged leads, trip incidents | Overhead reel or cable ramps |
| Charging during lifting operations | Lead snagged by a load or vehicle | Define an exclusion zone around the charge point |
| Assumption that a full charge fits the night | Machine partially charged at shift start | Measure the actual charge time; consider a higher-power charger |
| No spare battery for a 24-hour operation | Machine idle for hours | Spare battery and a handling method, or a second machine |
Frequently asked questions
Can I charge an electric platform from a standard site socket?
Only if the charger's input current is within the circuit rating and nothing else shares it. Most sites need a dedicated circuit, because the charging load coincides with other end-of-shift loads.
How long does a full charge take?
It depends on battery capacity and charger power. Ask for both figures and calculate; do not rely on a general statement such as overnight.
Is opportunity charging bad for the battery?
For lead-acid, frequent partial charging without periodic full charges causes sulphation. For lithium, opportunity charging is normal and beneficial. The strategy must match the chemistry.
Do I need a spare battery?
For a single-shift operation, usually not. For continuous or multi-shift operation, a spare battery or a second machine is the practical way to keep the work moving.
What ambient temperature affects charging?
Both very high and very low temperatures reduce charging efficiency and can damage some chemistries. Confirm the charger and battery operating range against the site climate.
Can charging be scheduled automatically?
Yes, where the charger has a timer or the site has load management. Staggered start times are the simplest way to avoid a peak load.
What should be included in the site induction for operators?
Charge point location, connector handling, cable management, the exclusion zone, and the procedure for reporting a charging fault. Four points are usually enough.
}Specify the machine before you plan the site
Charging infrastructure follows from the machine specification: battery capacity, charger power and duty cycle. Our procurement and acceptance guide covers the fields that must be unambiguous in the purchase order.
Need a seat matched to your machine?
Send us the mounting dimensions, vehicle model and operating conditions. We will confirm the suspension type, adjustment range and mounting plate that fit, and quote accordingly.